COVID-19 - Learn about COVID-19 public health measures and get vaccinated.

Notice of construction: Grimsby Watermain Replacement - Phase 2

Niagara Region is proceeding with transmission watermain upgrades along South Service Road / Clarke Street (Regional Road 40) in Grimsby.

The length of the watermain segment that will be constructed during this phase is approximately 850 metres. Construction will begin summer or fall of 2022 and continue through the spring of 2023 at the following locations:

  • South Service Road (​Regional Road 40) between Baker Road N and Park Road N
  • Trenchless crossing of the CN Railway at Park Road N
  • Elizabeth Street between Clark Street and CN Railway
  • Isolated locations between Elizabeth Street and Park Road

Lane restrictions, lane closures and road closures resulting in travel delays are expected and ongoing. Alternate routes around the construction zone will be posted and should be taken.

Your co-operation and patience during this period of inconvenience will be appreciated.

Any inquiries concerning this project may be directed to:

Mark Belanger, CET, P.Eng
Consultant, Associated Engineering
289-974-0359
belangerm@ae.ca

Gino Giancola, B.Sc., CET, PMP®
Project Manager Water & Wastewater Engineering
905-980-6000 ext. 3735
1-800-263-7215

Niagara Region Dispatch
905-984-3690

Periodic updates will be made available through the Grimsby Watermain Replacement project page and the Town of Grimsby’s website.

Page Feedback Did you find what you were looking for today?