Annual Strengthening and Resurfacing Program

Niagara Region maintains 1,738 kilometres of roadway across Niagara. Keeping these roads in safe and optimal conditions requires ongoing review and maintenance.

Each year, we inspect one-third of the regional road network. Our focus is on regular preventative maintenance which can extend the life of a roadway.

Our strengthening and resurfacing program increases the lifespan of road sections by improving the structural integrity. The program includes:

  • Replacing selected cross culverts
  • Milling off the top course of asphalt or doing a cold in place strategy of the road section
  • Repairing cracks in the base course asphalt and replacing concrete curbs that are in poor condition
  • Paving new top course asphalt, line marking and adding granular to shoulders
  • Waterproofing existing culvert structures

Contact

Stephanie Huppunen
Manager, Capital Projects
Email Stephanie Huppunen

Strengthening and resurfacing projects

Fort Erie

  • Stevensville Road (Regional Road 116) - completed

    Location: Stevensville Road (Regional Road 116)

    Limits: Eagle Street to Netherby Road (Regional Road 25)

    Impact:

    • Work hours from 7 a.m. to 7 p.m.
    • Single-lane closures
    • Longer than normal wait times

    Date: To be determined

    Contractor: Brennan Paving

Fort Erie / Niagara Falls

  • Netherby Road (Regional Road 25) - completed

    Location: Netherby Road (Regional Road 25)

    Limits: Crowland Avenue to Point Abino Road North

    Impact:

    • Partial road closure from Doan's Ridge Road (Regional Road 84) to Montrose Road (Regional Road 98)

    Detour route:

    • Doan's Ridge Road (Regional Road 84) > Schisler Road (Regional Road 27) > Montrose Road (Regional Road 98)

    Date: Sept. 19 and 20, 2024

    Contractor: Brennan Paving

Niagara Falls

  • Kalar Road (Regional Road 98) - completed

    Location: Kalar Road (Regional Road 98)

    Limits: Montrose Road (Regional Road 98) to Mountain Road (Regional Road 101)

    Impact:

    • Single-lane closures
    • Longer than normal wait times

    Date: Mid June to Early September

    Contractor: Brennan Paving - Niagara

  • Lundy's Lane (Regional Road 20) - completed

    Location: Lundy's Lane (Regional Road 20)

    Limits: Dorchester Road to Drummond Road

    Impact:

    • Night work hours from 7 p.m. to 7 a.m.
    • Single-lane closures
    • Longer than normal wait times

    Date: Mid / end of April through May

    Contractor: Rankin Construction

  • Montrose Road (Regional Road 98) - completed

    Location: Montrose Road (Regional Road 98)

    Limits: Thorold Stone Road (Regional Road 57) to Highway 420

    Impact:

    • Single-lane closures
    • Longer than normal wait times

    Date: To be determined

    Contractor: Rankin Construction

  • Thorold Stone Road (Regional Road 57) - completed

    Location: Thorold Stone Road (Regional Road 57)

    Limits: Thorold Townline Road (Regional Road 70) to Kalar Road

    Impact:

    • Lane closures
    • Longer than normal wait times

    Date: Mid June to Early September

    Contractor: Brennan Paving - Niagara

Lincoln

  • King Street (Regional Road 81) - completed

    Location: King Street (Regional Road 81)

    Limits: Thirteenth Street to Eleventh Street

    Impact:

    • Nightly work from 7 p.m. to 7 a.m.
    • Single-lane closures
    • Longer than normal wait times

    Date: Mid June to Early September

    Contractor: Brennan Paving - Niagara

Pelham

  • Victoria Avenue (Regional Road 24) - completed

    Location: Victoria Avenue (Regional Road 24)

    Limits: Canborough Road (Regional Road 63) to Highway 20

    Impact:

    • Work hours from 7 a.m. to 7 p.m.
    • Single-lane closures
    • Longer than normal wait times

    Contractor: Walker Construction

St. Catharines

  • Niagara Street (Regional Road 48) - completed

    Location: Niagara Street (Regional Road 48)

    Limits: Carlton Street to Lakeshore Road (Regional Road 87)

    Impact:

    • Work hours from 7 a.m. to 7 p.m.
    • Large patching single-lane closures
    • Longer than normal wait times

    Contractor: Rankin Construction

Wainfleet

  • Creek Road (Regional Road 45) - completed

    Location: Humberstone Road (Regional Road 33)

    Limits: Intersection of Creek Road (Regional Road 45) and Dilts Road

    Impact:

    • Work hours from 7 a.m to 7 p.m.
    • Large patching single-lane closures
    • Longer than normal wait times

    Contractor: Rankin Construction

Welland

  • Humberstone Road (Regional Road 33) - completed

    Location: Humberstone Road (Regional Road 33)

    Limits: Highway 58 to Landfill Site

    Impact:

    • Nightly work from 6 p.m. to 6 a.m.
    • Single-lane closures
    • Longer than normal wait times

    Date: Mid June to Early September

    Contractor: Brennan Paving - Niagara