Construction of Thorold Stone Road (Regional Road 57) Extension from Limit to Roundabout
All Niagara Region projects
About the project
Niagara Region is extending Thorold Stone Road (Regional Road 57) where it currently ends at the Gale Centre entrance (Phase 1) to the Victoria Avenue and Bridge Street (Regional Road 43) intersection with a roundabout (Phase 2).
The extension will provide:
- A key connection to the QEW
- An improved east / west linkage to the City of Niagara Falls' downtown area and Niagara River Parkway
- Economic growth and redevelopment of a significant brownfield for the City of Niagara Falls
With improved transportation connectivity and daily GO train service to Niagara Falls by 2023, there's an opportunity to leverage and enhance the land uses. This will ensure it's an attractive arrival point for commuters and visitors.
Niagara Region is working with the City of Niagara Falls to determine a vision for the GO Station area. This includes road, transit, public realm and active transportation options for the Bridge Street / GO Station area as identified in the approved Niagara Falls Transit Station Secondary Plan.
Construction of the roundabout is now complete. The extension of the Thorold Stone Road (Regional Road 57) project is targeted for construction commencement in late 2025 / early 2026, pending budget approvals.
Complete Streets
We'll integrate design elements that support the Complete Streets Design Guidelines for Niagara. The guidelines will focus on enhancing the functionality of boulevards and roadway safety.
The goal is to provide an innovative and creative solution that is:
- Environmentally sustainable
- Attracts growth on adjacent lands
- Supports active transportation and other modes of mobility to help people of all ages travel throughout Niagara
Project timeline
april 2021 - completed
Start utility relocations
December 2021 - completed
Public Information Centre #1
Winter 2021 - completed
Complete utility relocations
Winter 2021 - completed
Roundabout tender closes
Winter / Spring 2022 - completed
Start roundabout construction
Summer 2022 - completed
Complete roundabout construction
Winter 2024
Start detailed design of Thorold Stone Road extension
Late 2025 / early 2026
Start construction of Thorold Stone Road extension, pending budget approval
Contact
Stephanie Huppunen, C.E.T.
Manager, Capital Projects, Transportation Engineering
Niagara Region
Email Stephanie Huppunen
Reports and Documents
- Report - Extension of Thorold Stone Road (Regional Road 57)
- Notice of Public Information Centre #1 for the proposed roundabout at Victoria Avenue and Bridge Street (Regional Road 43)
Public Information Centre #1 - December 2021