Port Dalhousie Wastewater Treatment Plant
All Niagara Region projects

About the project

The Port Dalhousie Wastewater Treatment Plan is owned and operated by Niagara Region, located at 40 Lighthouse Rd., in St. Catharines (north of Lakeshore Road), servicing St. Catharines and Thorold.

The Port Dalhousie Wastewater Treatment Plant requires improvements throughout the plant, which will be completed in phases under two contracts.

Project updates

  • Contract One

    The scope of work associated with contract one includes:

    • Construction of two new aeration tanks consisting of fine bubble diffuser system, coarse bubble channel and chamber aeration, aeration tanks influent chamber and aeration tanks Mixed Liquor Suspended Solids chamber
    • Construction of a new blower building and installation of new blowers and controls
    • Replacement of existing secondary clarifier five Return Activated Sludge pumps and associated piping and instrumentation with new
    • Modifications to existing primary power distribution system, addition of a new switchgear, transformer and generator
    • Installation of new Remote Programmable Unit and supervisory control and data acquisition upgrades
    • Decommissioning of the existing aeration system
  • Contract Two

    The scope of work associated with contract two includes:

    • Construction of new inlet/bypass channels with flow measurement
    • Modifications to existing screen building including installation of new screening conveyance system
    • Modifications to the chlorine contact tank inlet and gates
    • Refurbishment of the existing biofilter
    • Construction of a new administration building
    • Demolition of a portion of the existing administration building
    • Replacement and/or rehabilitation of the plant Master Control Centres
    • Replacement of the plant Remote Programmable Units

Project timeline

2020 - Completed
Detailed design

march 2021 to March 2024 - completed
Construction of Contract One

February 2024 - completed
Substantial completion of Contract One

March 2023 to August 2025
Design of Contract Two

January 2026 - January 2028
Construction for Contract Two

 

Contact

Lindsay Jones
Manager Capital Projects
Niagara Region
905-321-1925
Email Lindsay Jones

Stephan Gazzola
Project Manager
Niagara Region
905-933-8526
Email Stephan Gazzola

Bob Crigger
Project Manager and Contract Administrator
Hatch Ltd.
905-599-5513
bob.crigger@hatch.com

Image Gallery


Aeration tank one and two excavation construction
Aerial overview of the construction site in February 2024
Map of the Port Dalhousie Wastewater Treatment Plant
Aeration tank one and two excavation construction
Aeration tank one and two excavation progress
Aeration tanks one and two
Aerial view of aeration tank one and two
Aerial view of the construction site in August 2022
Placing the blower building footing concrete
Blower building footing reinforcing steel
Bulk excavation aeration tanks construction
Shoring installation on the west side of the aeration tanks