Cole Farm Sewage Pumping Station
All Niagara Region projects

About the project

The Cole Farm Sewage Pumping Station at 26 Colton Ave. in St. Catharines is owned and operated by Niagara Region. The station services a catchment area of approximately 100 hectares for nearby residents and businesses.

The station was constructed in 1978 with minor upgrades completed in 1992. Key components have been in service for over 30 years and are past their service life.

The scope of work includes:

  • Demolishing the existing building and installing a new covered shelter
  • Underground infrastructure replacement
  • A new 600 metres long forcemain that will run from the pumping station, along Colton Avenue and Corbett Avenue to Main Street
  • Pump and process piping and equipment replacement
  • New outdoor generator
  • Electrical, instrumentation and communication upgrades
  • Site work improvements

Local impacts during construction

  • Traffic

    Expect moving block by block lane restrictions and road closures that cause traffic delays.

  • Access

    Access to your home or business will remain. We will notify you in advance if construction blocks your driveway for a short period and arrange accommodations. Email Dana Knegt any concerns with not having access during construction

    The waterfront trail will remain accessible throughout construction, but will be rerouted outside the construction area.

    There will be public access to walk along the outside of the construction site. Avoid any non-essential activities in the construction area if possible. Use extra caution when entering the construction area. Read and obey all warning signs, avoid heavy equipment and stay visible to all workers and vehicles.

Project timeline

2020 - completed
Detailed design

July 2022 - completed
Request for pre-qualification

December 2022 to February 2023 - completed
Request for tender

April 2023 - completed
Project award to general contractor

Q1 2024 to Q3 2025 - Completed
Construction

Contact

Dana Knegt, C.Tech
Niagara Region
Project Manager
289-929-8451
Email Dana Knegt

Mark Belanger, CET, P.Eng.
Associated Engineering
Project Manager
289-974-0359
belangerm@ae.ca

Project updates

The contractor provided a notice of construction and a pre-construction survey to residents and businesses and completed all authorized surveys. All post-construction surveys have been completed.

Construction started in spring 2024 and was substantially completed in fall 2025.

Most of the work took place at the sewage pumping station. The new sanitary forcemain installation extended from the station along Colton Avenue and Corbett Avenue to Main Street.