Structural Rehabilitation of Sixteen Mile Creek Arch Culvert
All Niagara Region projects
About the project
Niagara Region is working to improve safety and road stability on Fourth Avenue (Regional Road 77) in Lincoln. Inspections found erosion around a culvert that carries Sixteen Mile Creek under the road. There are also concerns about slope stability. Steps are being taken to address these issues.
This work is part of the Region's ongoing commitment to keep infrastructure safe and reliable across the community.
Project timeline
Spring 2025 - Completed
Detailed design
April 13, 2026 - Completed
Pre-construction Public Information Centre
May 2026
Start construction
Fall 2026
Finish construction
Contact
Alex Villella, C.E.T.
Project Manager, Transportation Engineering
Niagara Region
905-980-6000 ext. 3063
Email Alex Villella
Reports and Documents
- Notice of pre-construction Public Information Centre
- Notice of road closure for Fourth Avenue (Regional Road 77)
Public Information Centre - April 13, 2026