Regional Rd. 98 Reconstruction
All Niagara Region projects

About the Project

We're planning the reconstruction of Regional Road 98 (Montrose Rd.) from Regional Road 49 (McLeod Rd.) to Charnwood Ave.

In 2011, Niagara Region (along with the City of Niagara Falls), completed a Municipal Class Environmental Assessment which identified the need to reconstruct Montrose Rd. to address traffic capacity issues, safety and operational improvements, active transportation and complete streets. Between 2016 and 2019, the detailed design for the reconstruction was completed.

The project will include the following items:

  • New sewers and water mains
  • New curbs
  • New sidewalks
  • Multi-use pathway
  • New asphalt
  • Traffic signals
  • Landscaping

Project Timeline

2016
Design commences

2018
Detailed design for reconstruction complete

march 2019
Project tendered

june 2019
Construction starts

december 2019
Major construction works complete

spring 2020
Final asphalt and restoration

 

Contact

Graeme Guthrie
Senior Project Manager
905-980-6000 ext. 3249
Email Graeme Guthrie