Reconstruction of Canborough Road (Regional Road 63)
All Niagara Region projects
About the project
Niagara Region is reconstructing Canborough Road between Wellandport Road (Regional Road 27) and the Wellandport Community Centre.
The reconstruction will address:
- Road conditions
- Storm drainage and infrastructure improvements
- Active transportation and complete streets
Streetscaping, landscaping and urban design improvements will be complete in partnership with West Lincoln.
Project timeline
March 2023
Retain consultant and start detailed design
Summer 2024
Move utilities and get property
Winter 2025
Issue tender for construction (pending budget approval)
SPRING 2025
Start construction
SPRING 2026
Finish construction
Contact
Mike Keller
Niagara Region
Project Manager
905-980-6000 ext. 3265
Email Mike Keller