The reconstruction of Ontario St. (Regional Rd. 42) between Linwell Rd. and Lakeport Rd. (Regional Rd. 87) will be completed as part of a Municipal Class Schedule "C" Environmental Assessment, which identified the need for improvement in traffic operations, capacity and safety, all of which will be addressed.
The work to be completed include the reconstruction and widening of intersections on the roadway, new storm sewer/culvert replacement, upgraded illumination and watermain work will also be completed on behalf of the City of St. Catharines.
february 2021
Syphon investigation and clean out
july 2021
Utility relocations commence
december 2022
Utility relocations complete
january 2023
Issue tender for construction
april 2023
Construction commences
December 2023
Construction complete
Stephanie Huppunen
Project Manager
905-980-6000
Email Stephanie Huppunen
Businesses remain open
Temporary lane, sidewalk and driveway closures may happen from time to time, but access to businesses will be maintained at all times.
Expected traffic delays
Regional traffic will be kept open to through traffic during construction. However, throughout construction there will be temporary lane restrictions which will result in delays. Drivers can avoid delays by using alternative routes.