Intersection Improvements at Regional Rd. 27 and Regional Rd. 84
All Niagara Region projects

About the Project

This project will focus on intersection improvement at Regional Rd. 27 (East Main St. / Schisler Rd.) and Regional Rd. 84 (Moyer Rd. / Doan's Ridge Rd.). It will include construction of left turn lanes on all four legs of the intersection and a right turn lane on the north leg, traffic signal / intersection illumination upgrades, curb / gutter, culvert replacements and drainage improvements.

Brennan Paving and Construction Ltd. has been secured as the contractor for this project.

Project Timeline

october 2019 - Completed
Detailed design

may 2020 - Completed
Tender and award

september 2020 - completed
Construction begins

november 2020
Anticipated construction completion

Contact

Bradley McIntyre
Contract Administrator
905-980-6000 ext. 3370
Email Bradley McIntyre

Mike Keller
Project Manager
905-980-6000 ext. 3265
Email Mike Keller

Expected traffic delays

Throughout construction, there will be temporary lane restrictions which may result in delays.

Residents and motorists can avoid delays by using alternative routes.

All businesses will remain open and accessible.

Image Gallery


East Main Street

Reports and Documents

This image shows Regional Rd. 27 (Schisler Rd.) looking east.
Page Feedback Did you find what you were looking for today?