Niagara Region initiated a Schedule B Municipal Class Environmental Assessment study for the Catherine Street Sewage Pumping Station, located at 8 Catherine St. in Fort Erie. The station was built in 1981 and has since undergone various maintenance repairs.
Investigations conducted at the station show aging infrastructure that's in need of repair or replacement to ensure it will properly service the Town of Fort Erie. The current location of the pumping station and the neighbouring lot are owned by Niagara Region. Both locations will be considered for an upgraded station along with other alternatives.
The study will define the current and future needs as outlined in the Water and Wastewater Master Plan and evaluate alternative strategies to avoid or minimize impacts to the community and natural environment. The Master Plan indicates future capacity demands will increase due to operational, capacity and wet weather constraints. The study will follow the guidance outlined in the Municipal Class Environmental Assessment document (as amended in 2007, 2011 and 2015).
jan. 13, 2021 - Completed
Project initiation
february 2021
Notice of study commencement
spring 2021
Public information centre
fall 2021
Notice of study completion
Stephanie McGill
Project Manager
905-980-6000 ext. 3176
Email Stephanie McGill
Amanda Beattie
Project Manager, GM BluePlan
amanda.beattie@gmblueplan.ca