Bal Harbour Sanitary Pumping Station Upgrades
All Niagara Region projects
About the project
Niagara Region is undertaking a conceptual design for the Bal Harbour Pumping Station electrical upgrades located at 29B Cheval Dr. in Grimsby.
This project will install electrical cabinets and a small, quiet generator that services the station above the existing pump station chamber. This will promote easier access and the health and safety of operations and maintenance staff. These upgrades will improve the reliability of the pump station equipment in the case of utility power failure and wet weather flooding event.
The project design will consider the aesthetics of the station. Professional landscape architectural services will give a cohesive and functional layout for the new electrical equipment.
Project timeline
SPRING 2022 - Completed
Project kick-off
January 4-26, 2023 - completed
Online Public Information Centre #1
Spring 2024 - Completed
Detailed design
August 19 to September 3, 2024 - completed
Online Public Information Centre #2
Fall / winter 2024
Tender
Spring to winter 2025
Install new electrical equipment
Contact
John Lee P.Eng, PMP
Niagara Region
Project Manager, Water and Wastewater Engineering
905-980-6000 ext. 3136
Email John Lee
Brad Wilson, P.Eng.
Stantec Consulting Limited
Consultant Project Manager
519-590-5816
brad.wilson2@stantec.com
Reports and Documents
Public Information Centre #1 - Jan. 4-26, 2023
Public Information Centre #2 - Aug. 19 to Sept. 3, 2024