Baker Road Wastewater Treatment Plant
All Niagara Region projects

About the Project

Niagara Region, in partnership with the Town of Grimsby, the Town of Lincoln and the Township of West Lincoln, are preparing a Pollution Prevention and Control Plan as well as a Wastewater Master Servicing Plan update study.

The project's scope is to update the previous 2009 Baker Rd. Wastewater Treatment Plant Pollution Control Plan to meet the goals of the procedure F-5-5 and under the Class Environmental Assessment process for Master Plans, develop a prioritized action plan for improvements of the system supporting short and long-term growth and sustainability of the wastewater infrastructure.

Project Timeline

july 2019
Request for proposal issued

october 2019
Kick-off meeting

november 18, 2019
Technical memo #1 - background review

december 2, 2019
Technical memo #2 - flow monitoring program review, assessment and analysis

january 6, 2020
Technical memo #3 - hydraulic sewer model review and recommendations

january 20, 2020
Technical memo #4 - gap analysis

april 6, 2020
Public information centre #1

july 13, 2020
Technical memo #5 - updated hydraulic modellling analysis

august 2020
Filing of the final Pollution Prevention and Control Plan and Wastewater Master Servicing Plan for a 30-day review

august 24, 2020
Technical memo #6 - 10 year Capital Plan

august 24, 2020
Technical memo #7 - 75 year Capital Plan

september 2020
Filing of the final Pollution Prevention and Control Plan and Wastewater Master Servicing Plan for a 30-day review

september 21, 2020
Public information centre #2

 

Contact

Ilija Stetic
Project Manager
905-980-6000 ext. 3777
Email Ilija

Image Gallery


Baker Road Wastewater Treatment Plant System Map
Page Feedback Did you find what you were looking for today?