COVID-19 - As of Jan. 14, a stay at home order is in effect. See restrictions and public health measures. Get updates on COVID-19 and learn about service disruptions.

Baker Road Wastewater Treatment Plant
All Niagara Region projects

About the Project

Niagara Region, in partnership with the Town of Grimsby, the Town of Lincoln and the Township of West Lincoln, are preparing a Pollution Prevention and Control Plan as well as a Wastewater Master Servicing Plan update study.

The project's scope is to update the previous 2009 Baker Rd. Wastewater Treatment Plant Pollution Control Plan to meet the goals of the procedure F-5-5 and under the Class Environmental Assessment process for Master Plans, develop a prioritized action plan for improvements of the system supporting short and long-term growth and sustainability of the wastewater infrastructure.

This study will satisfy Phase 1 and 2 of the Municipal Engineers Association Class Environmental process (October 2000, as amended in 2007, 2011 and 2015). This is an approved process under the Ontario Environmental Assessment Act and will evaluate alternatives to help support the long-term sustainability of the wastewater systems.

Project Timeline

july 2019 - completed
Request for proposal issued

oct. 2019 - completed
Kick-off meeting

nov. 18, 2019 - completed
Technical memo #1 - background review

dec. 2, 2019 - completed
Technical memo #2 - flow monitoring program review, assessment and analysis

feb. 11, 2020 - completed
Technical memo #3 - hydraulic sewer model review and recommendations

feb. 11, 2020 - completed
Technical memo #4 - gap analysis

sept. 25, 2020 - completed
Technical memo #5A - hydraulic modeling development

oct. 2, 2020 - completed
Technical memo #5B - flow monitoring stretch of time in two municipalities

nov. 2, 2020
Technical memo #5C - baseline system performance and growth analysis

nov. 9, 2020
Technical memo #6A - evaluation criteria

dec. 4, 2020
Technical memo #6B - alternatives evaluation
Technical memo #7 - 75 year plan

jan. 12, 2021
Technical memo #6C - 10-year Capital Plan

feb. 2, 2021
Public information centre #2

feb. 26, 2021
Draft Pollution Prevention and Control Plan Report

2021
Council Report

 

Contact

Ilija Stetic, B.Sc, PMP
Project Manager
905-980-6000 ext. 3777
Email Ilija

Public Engagement

Public engagement will be an important part of this project.

Niagara Region will host a public information centre on Feb. 2, 2021.

Full details on time and location will be posted once they become available.

Page Feedback Did you find what you were looking for today?