Capital Project Forecast - Quarter 2 Financial Update (2017) (in thousands of dollars)
A detailed analysis of capital sub-projects with budgets remaining greater than $1 million is presented below. There are a total of 191 projects totalling $964,481 of adjusted capital budget. Project spending to date on these sub-projects amounts to $549,646, representing 57.0 per cent of the adjusted capital budget on these sub-projects.
Project Description | Project Status | Adjusted Budget | Project-to-date Actuals | Budget Remaining | Forecasted Cashflows | Estimated Year of Completion | Outstanding Commitments (Purchase Orders) | |
---|---|---|---|---|---|---|---|---|
2017 | Beyond 2017 | |||||||
Community Services | ||||||||
Long-term Care Home Redevelopment | $3,515 | 183 | $ 3,332 | $ 200 | $3,132 | 2018 | $ 0 | |
Long-term Care Home Redevelopment | Uninitiated | 12,120 | - | 12,120 | - | 12,120 | 2018 | 0 |
Northland Pointe Siding Replacement | 4,700 | 3,182 | 1,518 | 500 | - | 2017 | 198 | |
Total Community Services | 20,335 | 3,365 | 16,970 | 700 | 15,252 | 198 | ||
Corporate Services | ||||||||
Asset Replacement - 2016 | 3,169 | 1,718 | 1,451 | 1,451 | - | 2017 | 631 | |
Asset Replacement - 2017 | 2,500 | 60 | 2,440 | 2,440 | - | 2017 | 8 | |
Customer Service Strategic Priority | 200 | - | 200 | 200 | - | 2018 | - | |
Customer Service Strategic Priority | Uninitiated | 1,485 | - | 1,485 | 300 | 1,185 | 2018 | - |
Financial Management System | 12,940 | 11,946 | 994 | 400 | 594 | 2018 | 220 | |
Information Technology Server Building | 3,945 | 2,113 | 1,832 | 1,832 | - | 2017 | 1,813 | |
Renewable Energy Program | 1,366 | 368 | 998 | 994 | - | 2017 | 4 | |
Total Corporate Services | 25,605 | 16,205 | 9,400 | 7,616 | 1,779 | 2,675 | ||
Court Services | ||||||||
Court Facilities Renewal | 13,390 | 8,237 | 5,153 | 5,185 | - | 2017 | 3,681 | |
Court Facilities Renewal | Uninitiated, on hold |
13,210 | - | 13,210 | - | - | 2017 | - |
Total Court Services | 26,600 | 8,237 | 18,363 | 5,185 | - | 3,681 | ||
Niagara Regional Housing | ||||||||
Building Capital - 2015 | 2,045 | 1,824 | 222 | 168 | - | 2017 | 148 | |
Building Capital - 2016 | 2,443 | 2,370 | 72 | 6 | - | 2017 | 6 | |
Building Capital - 2017 | 1,987 | 506 | 1,480 | 1,480 | - | 2017 | 980 | |
Fitch Street, Welland | 9,983 | 9,489 | 493 | - | - | 2017 | - | |
Grounds Capital - 2017 | 1,053 | 121 | 932 | 931 | - | 2017 | 653 | |
NRH Carlton Street, St. Catharines | 4,179 | 1,939 | 2,240 | 2,240 | - | 2019 | 31 | |
NRH Carlton Street, St. Catharines | Uninitiated | 11,592 | - | 11,592 | 3,710 | 7,851 | 2019 | - |
NRH Social Housing Improvement Program - 2016 | 1,200 | 427 | 773 | 773 | - | 2017 | 697 | |
Unit Capital - 2015 | 2,622 | 1,710 | 912 | 323 | - | 2017 | 23 | |
Unit Capital - 2016 | 2,390 | 2,012 | 377 | 341 | - | 2017 | 341 | |
Unit Capital - 2017 | 4,665 | 259 | 4,406 | 2,793 | 1,578 | 2018 | 793 | |
Total Niagara Regional Housing | 44,157 | 20,658 | 23,500 | 12,765 | 9,429 | 3,672 | ||
Niagara Regional Police Services | ||||||||
Communications Unit Back-up | 1,000 | - | 1,000 | - | 1,000 | 2017 | - | |
Communications Unit Back-up | Uninitiated | 1,250 | - | 1,250 | - | 1,250 | 2017 | - |
Communications Unit Equipment | 4,500 | 4,451 | 49 | 49 | - | 2017 | 43 | |
Information Technology Continuity Plan | 1,500 | 566 | 934 | 500 | 434 | 2018 | - | |
Long-term Accommodations - Headquarters D2 | 69,700 | 68,908 | 792 | 792 | - | 2018 | 860 | |
Long-term Accommodations - Headquarters D1 | Uninitiated | 13,376 | - | 13,376 | - | 13,376 | 2018 | - |
Long-term Accommodations - 2017 D1 | Uninitiated | 5,653 | 1 | 5,652 | (1) | - | 2017 | - |
S.P.I.R.I.T. (Supporting Police in Records Information Technology) | 8,630 | 8,393 | 237 | 137 | 100 | 2018 | 38 | |
Vehicles - 2013 | 1,300 | 1,292 | 8 | 8 | - | 2017 | 0 | |
Vehicles - 2014 | 1,423 | 1,423 | (0) | (0) | - | 2017 | - | |
Vehicles - 2015 | 1,400 | 1,398 | 2 | 2 | - | 2017 | 0 | |
Vehicles - 2016 | 1,400 | 1,298 | 102 | 102 | - | 2017 | 72 | |
Vehicles - 2017 | 1,400 | 500 | 900 | 700 | 200 | 2018 | 483 | |
Voice Radio System | 13,315 | 13,124 | 190 | 190 | - | 2017 | (0) | |
Total Niagara Regional Police Services | 125,847 | 101,355 | 24,492 | 2,479 | 16,360 | 1,496 | ||
Planning | ||||||||
HQ Landscape Master Plan - 2017 | 1,159 | - | 1,159 | 250 | 909 | 2018 | - | |
Total Planning | 1,159 | - | 1,159 | 250 | 909 | - | ||
Public Health | ||||||||
Ambulance & Equipment - 2015 | 2,222 | 2,030 | 192 | 1 | - | 2017 | 1 | |
Ambulance & Equipment - 2016 | 1,766 | 1,456 | 311 | 283 | - | 2017 | 133 | |
Ambulance & Equipment - 2017 | 1,812 | - | 1,812 | 132 | 1,680 | 2018 | 132 | |
Emergency Medical Services Facility | 3,100 | 1,663 | 1,437 | 200 | 900 | 2018 | 34 | |
Emergency Medical Services Equipment - 2015 | 2,262 | 2,185 | 78 | 78 | - | 2017 | (0) | |
Emergency Medical Services Central Hub | Uninitiated | 3,895 | - | 3,895 | - | 3,895 | 2017 | - |
Health Facilities - Niagara Region | 4,665 | 902 | 3,763 | 2,740 | 1,023 | 2018 | 98 | |
Health Facilities - Niagara Region | Uninitiated | 3,500 | - | 3,500 | - | 3,500 | 2018 | - |
Total Public Health | 23,223 | 8,235 | 14,988 | 3,434 | 10,998 | 398 | ||
Public Works - Levy | ||||||||
Annual - Transportation Master Plans | 1,435 | 1,298 | 137 | 137 | - | 2017 | 99 | |
Annual - Storm Sewer Program | 1,500 | - | 1,500 | 1,500 | - | 2017 | - | |
Capacity Improvements - New Escarpment Crossing | 2,200 | 683 | 1,517 | 1,510 | - | 2017 | 6 | |
Capacity Improvements - Charnwood - McLeod | 2,300 | - | 2,300 | 300 | 2,000 | 2018 | - | |
Capacity Improvements - RR54 Hwy 20/Merritt | 9,100 | 509 | 8,591 | 7,000 | 1,591 | 2018 | 465 | |
Capacity Improvements - Reconstruct Hwy 406 @ Third Interchange | 1,460 | 727 | 733 | - | 733 | 2018 | - | |
Capacity Improvements - Reconstruct QEW @ Glendale Ave Interchange | 1,000 | 7 | 993 | 30 | 1,000 | 2019 | - | |
Capacity Improvements - Reconstruct RR49 (McLeod), Montrose to Stanley | 11,476 | 863 | 10,613 | 7,000 | 3,462 | 2018 | 151 | |
Capacity Improvements - Reconstruct RR49 Concession 6/Eastwest Line | 4,500 | 2,090 | 2,410 | 2,000 | 410 | 2018 | 1,821 | |
Capacity Improvements - Reconstruct RR89 Homer/NOTG | 2,808 | 2,381 | 427 | 100 | - | 2017 | 234 | |
Intersection - King at Greenlane and Durham (Roundabout) | 3,039 | 2,518 | 520 | 125 | 250 | 2018 | 73 | |
Intersection - RR20 Industrial Park/South Grimsby Road 6 | 2,802 | 1,618 | 1,184 | 1,184 | - | 2017 | 1,121 | |
Intersection - RR20 Lundys Lane/Garner Road | 1,400 | 1,443 | (43) | - | - | 2017 | - | |
Intersection - RR46 Geneva/St. Paul | 7,000 | 179 | 6,821 | 5,000 | 1,821 | 2018 | 59 | |
Intersection - RR89 Jacobsen/Burleigh | 7,500 | 1,913 | 5,587 | 5,000 | 587 | 2018 | 4,636 | |
Replacement of Burgoyne Bridge | 93,344 | 93,344 | 0 | - | - | 2017 | 904 | |
Roads Facility Program | 1,500 | 306 | 1,194 | - | 1,194 | 2018 | 3 | |
Roads Reconstruction - RR20 Station/Rice | 3,793 | 3,441 | 352 | - | 35 | 2017 | 4 | |
Roads Reconstruction - RR3 Central/Concession | 2,446 | 2,348 | 97 | 92 | - | 2017 | 5 | |
Roads Reconstruction - RR38 QEW/Fourth | 3,210 | 2,056 | 1,154 | 1,054 | 100 | 2018 | 849 | |
Roads Reconstruction - RR50 Thorold/Riverbank | 2,400 | 668 | 1,732 | 1,731 | - | 2017 | 0 | |
Roads Rehabilitation - RR1 Albert/Lakeshore | 1,125 | 450 | 675 | 675 | - | 2017 | 166 | |
Roads Rehabilitation - RR1 Dominion Road, Burleigh/Buffalo | 12,165 | 780 | 11,385 | 5,000 | 6,385 | 2018 | 10,367 | |
Roads Rehabilitation - RR14 RR20/Townline | 6,880 | 6,843 | 37 | 20 | - | 2017 | 1 | |
Roads Rehabilitation - RR18 (Mountain), George to King | 8,245 | 7,514 | 732 | 732 | - | 2017 | 653 | |
Roads Rehabilitation - RR45 RR4/RR63 | 1,775 | 250 | 1,525 | 100 | - | 2017 | 152 | |
Roads Rehabilitation - RR57 Stanley Whirlpool/Valleyway | 14,951 | 14,608 | 343 | 100 | - | 2017 | 212 | |
Roads Rehabilitation - RR57 | 9,700 | 7,526 | 2,174 | 600 | 1,522 | 2018 | 248 | |
Roads Rehabilitation - RR69 Effingham/Wessel Phase 2 | 9,100 | 249 | 8,851 | 400 | 8,451 | 2018 | 214 | |
Roads Rehabilitation - RR87 Lake/Geneva | 6,841 | 5,605 | 1,236 | 1,000 | 236 | 2018 | 1,117 | |
Roads Rehabilitation - RR87 Lakeport/Lake | 5,638 | 5,584 | 54 | 54 | - | 2017 | 72 | |
Roads Rehabilitation - RR87 Third/Seventh | 1,500 | 268 | 1,232 | 732 | 500 | 2018 | 252 | |
Roads Rehabilitation - RR87 Townline/Four Mile Creek | 2,950 | 390 | 2,560 | 1,242 | 1,319 | 2018 | 742 | |
Roads Resurfacing - 2013 | 4,924 | 4,189 | 735 | 460 | - | 2017 | - | |
Roads Resurfacing - 2015 | 8,646 | 8,146 | 500 | 340 | - | 2017 | 340 | |
Roads Resurfacing - 2016 | 9,800 | 7,063 | 2,737 | 2,584 | - | 2017 | 2,584 | |
Roads Resurfacing - 2017 | 12,500 | 1,195 | 11,305 | 8,000 | 3,305 | 2018 | 5,750 | |
Stabilization RR14 Canboro Rd at Warner | 5,090 | 1,430 | 3,660 | 2,000 | 1,659 | 2018 | 134 | |
Structural Rehabilitation - Main Street Bridge | 4,703 | 4,405 | 298 | 298 | - | 2017 | 112 | |
Structural Rehabilitation - Reece Bridge | 8,033 | 664 | 7,368 | - | 7,368 | 2018 | 147 | |
Structural Rehabilitation - Central Ave Bridge over CNR | 16,940 | 16,822 | 118 | 118 | - | 2017 | 181 | |
Structural Rehabilitation - Ontario Power Generation Bridges over Gibson Lake | 8,100 | 7,942 | 158 | 50 | 50 | 2018 | 57 | |
Structural Rehabilitation - RR81 St Paul West CNR Bridge | 1,000 | 50 | 950 | 150 | 800 | 2018 | 4 | |
Structural Rehabilitation - 2016 Program | 3,700 | 1 | 3,699 | 1,500 | 2,199 | 2018 | 254 | |
GO Transit | 11,598 | 4,433 | 7,165 | 255 | 6,910 | 2023 | - | |
GO Transit | Uninitiated | 28,402 | - | 28,402 | - | 28,402 | 2023 | - |
Inter-municipal Transit - Capital Acquisitions - 2015 | Uninitiated | 1,340 | - | 1,340 | 1,340 | - | 2017 | - |
Inter-municipal Transit - Capital Acquisitions -2010 | 3,700 | 3,562 | 138 | - | - | 2017 | 85 | |
Vehicles - 2016 | 3,543 | 2,787 | 756 | 752 | - | 2017 | 752 | |
Vehicles - 2017 | 1,200 | 18 | 1,182 | 520 | 300 | 2018 | 245 | |
Total Public Works - Levy | 380,301 | 231,163 | 149,137 | 62,786 | 82,590 | 35,271 | ||
Waste Management | ||||||||
Bridge St - Public Drop Off Depot Improvement | Uninitiated | 1,145 | - | 1,145 | 285 | 860 | 2018 | - |
Humberstone - Landfill Gas Collection | 5,950 | 4,274 | 1,676 | 237 | 1,243 | 2019 | 237 | |
Recycling Centre - Facility Improvements | 1,600 | 894 | 706 | 558 | - | 2017 | 23 | |
Recycling Centre - Facility Improvements Groundwater | 1,123 | 951 | 172 | - | 110 | 2018 | 60 | |
Recycling Centre - Facility Improvements Optical Sorter | 2,718 | 2,630 | 87 | - | - | 2017 | - | |
Total Waste Management | 12,536 | 8,749 | 3,786 | 1,080 | 2,213 | 320 | ||
Wastewater | ||||||||
Centralized Maintenance Facility Improvements | 500 | 0 | 500 | 250 | 250 | 2018 | - | |
Centralized Maintenance Facility Improvements | Uninitiated | 500 | - | 500 | - | 500 | 2018 | - |
Combined Sewer Overflow (CSO) - Tank Construction - Chippawa | 9,511 | 9,148 | 363 | 150 | - | 2017 | (0) | |
Combined Sewer Overflow (CSO) - Grimsby | 1,725 | 222 | 1,503 | - | 1,503 | 2017 | - | |
Miscellaneous Program - Garner Road | 3,500 | 31 | 3,469 | 2,000 | 1,469 | 2018 | 106 | |
Pump Station Capacity Expansion Program - Odour Control - Smithville | 1,500 | 52 | 1,448 | 1,448 | - | 2017 | 122 | |
Pump Station Improvement Program - Carleton Street | 2,000 | 163 | 1,837 | 837 | 1,000 | 2018 | 1,800 | |
Pump Station Improvement Program - Clarke Street | 1,900 | 1,581 | 319 | - | - | 2017 | 86 | |
Pump Station Improvement Program - Design | 5,750 | 1,813 | 3,937 | 2,500 | 1,437 | 2020 | 3,648 | |
Pump Station Improvement Program - Fretz Street | 1,760 | 1,741 | 19 | - | - | 2017 | 0 | |
Pump Station Improvement Program - Jordan Valley | 1,610 | 1,523 | 87 | - | - | 2017 | 38 | |
Pump Station Improvement Program - NOTL, Garrison Rd, William St | 3,667 | 3,117 | 551 | 400 | 151 | 2018 | - | |
Pump Station Improvement Program - Old Orchard | 3,500 | 386 | 3,114 | 1,000 | 2,114 | 2018 | 1,883 | |
Pump Station Improvement Program - Ontario Street | 4,643 | 4,594 | 49 | 49 | - | 2017 | 36 | |
Pump Station Improvement Program - South Side High Lift | 6,651 | 6,053 | 597 | 597 | - | 2017 | 540 | |
Pump Station Improvement Program - Victoria Avenue | 3,600 | 3,264 | 336 | 331 | - | 2017 | 331 | |
Pump Station Improvement Program - Wellandvale | 2,124 | 1,339 | 785 | 60 | 725 | 2018 | 59 | |
Pump Station Improvement Program - Woodsview | On hold | 2,420 | 271 | 2,149 | - | - | 2017 | 65 |
Sewer & Forcemain Program - Confederation Park | 1,825 | 1,706 | 119 | 59 | - | 2017 | 60 | |
Sewer & Forcemain Program - Highway 406 Trunk | 1,450 | 0 | 1,450 | 450 | 1,000 | 2018 | - | |
Sewer & Forcemain Program - Oaks Park Trunk | 1,464 | 62 | 1,402 | 350 | 1,052 | 2018 | 3 | |
Sewer & Forcemain Program - Park Road | 13,940 | 12,076 | 1,864 | 379 | - | 2017 | 379 | |
Sewer & Forcemain Program - Stamford Centre | 4,550 | 180 | 4,370 | 1,089 | 3,281 | 2018 | 13 | |
Sewer & Forcemain Program - Victoria Ave | 4,400 | 3,557 | 843 | 787 | - | 2017 | 787 | |
Sewer Relining Program | 1,453 | 1,314 | 139 | - | 139 | 2017 | - | |
Wastewater Treatment Plant - Capacity Expansion - Niagara-on-the-Lake | 47,432 | 44,011 | 3,421 | 1,700 | 1,721 | 2019 | 2,374 | |
Wastewater Treatment Plant Bar Screen Program - Port Weller | 2,915 | 2,424 | 491 | 200 | - | 2017 | 334 | |
Wastewater Treatment Plant Digester/Sludge Management | 1,000 | 891 | 109 | 109 | - | 2017 | - | |
Wastewater Treatment Plant Upgrade - Garner Road | 2,200 | 72 | 2,128 | 39 | 2,089 | 2018 | 39 | |
Wastewater Treatment Plant Upgrade - Niagara Falls | 2,100 | 64 | 2,036 | 250 | 1,786 | 2018 | 38 | |
Wastewater Treatment Plant Upgrade - Port Weller | 9,900 | 335 | 9,565 | 205 | 9,360 | 2019 | 626 | |
Wastewater Treatment Plant Upgrade - Port Weller 2017 | 1,310 | 13 | 1,297 | 800 | 500 | 2018 | 59 | |
Wastewater Treatment Plant Upgrade - Welland | 20,750 | 6,175 | 14,575 | 4,000 | 10,575 | 2018 | 14,393 | |
Wastewater Treatment Plant Upgrade Program - Fine Bubble Aeration - Port Dalhousie | 14,500 | 645 | 13,855 | 300 | 13,555 | 2019 | 363 | |
Wastewater Treatment Plant Upgrade Program - Laneway Upgrades - Port Dalhousie | 2,000 | 1,791 | 209 | 59 | - | 2017 | 7 | |
Total Wastewater | 190,049 | 110,613 | 79,436 | 20,399 | 54,207 | 28,190 | ||
Water Works | ||||||||
Centralized Maintenance Facility Improvements | 500 | 0 | 500 | 250 | 250 | 2018 | - | |
Centralized Maintenance Facility Improvements | Uninitiated | 500 | - | 500 | - | 500 | 2018 | - |
Decommissioning obsolete equipment | 1,207 | 1,154 | 53 | 53 | - | 2017 | 53 | |
Miscellaneous Program - Evaluation & Replacement | 1,100 | 66 | 1,034 | 1,034 | - | 2017 | 956 | |
Miscellaneous Program - Pressure Booster | 1,308 | 110 | 1,198 | 59 | 1,138 | 2018 | 960 | |
Miscellaneous Program - System Storage - Grimsby | 15,339 | 436 | 14,903 | 550 | 14,353 | 2018 | 300 | |
Miscellaneous Program - System Storage - Port Colborne | 12,050 | 9,236 | 2,814 | 2,810 | 4 | 2018 | 2,810 | |
Water Treatment Plant Upgrade - Decew Falls - 2016 | 1,250 | 117 | 1,133 | 375 | 758 | 2019 | 1,013 | |
Water Treatment Plant Upgrade - Niagara Falls - 2013 | 5,250 | 3,520 | 1,730 | 100 | - | 2017 | 367 | |
Water Treatment Plant Upgrade - Niagara Falls - 2015 | 2,000 | 189 | 1,811 | 150 | 1,661 | 2018 | 46 | |
Water Treatment Plant Upgrade - Niagara Falls - 2017 | 4,320 | 3 | 4,317 | 2,000 | 2,317 | 2019 | 737 | |
Water Treatment Plant Upgrade - Port Colborne | 6,600 | 446 | 6,154 | 149 | 6,005 | 2019 | 149 | |
Water Treatment Plant Upgrade - Rosehill | 11,900 | 604 | 11,296 | 2,000 | 9,296 | 2019 | 45 | |
Water Treatment Plant Upgrade - Welland - 2008 | 25,106 | 23,203 | 1,903 | 903 | - | 2017 | 163 | |
Water Treatment Plant Upgrade - Welland - 20017 | 5,000 | 1 | 4,999 | 500 | 4,499 | 2020 | - | |
Watermain Program - Hwy406 Cross Trans | 1,525 | 4 | 1,521 | 521 | 1,000 | 2018 | - | |
Watermain Program - Fort Erie, Dominion Road | 10,615 | 421 | 10,194 | 3,000 | 7,194 | 2019 | 9,163 | |
Watermain Program - Welland East and West | 6,200 | 1,408 | 4,792 | 3,000 | 1,792 | 2018 | 597 | |
Valve & valve chamber replacement - 2013 | 2,900 | 153 | 2,747 | 625 | 2,122 | 2018 | 248 | |
Total Water Works | 114,670 | 41,070 | 73,600 | 18,080 | 52,889 | 17,608 | ||
Total Projects with remaining budgets greater than $1 million | $964,481 | $549,650 | $414,831 | $134,774 | $246,626 | $93,509 |