Capital Adjustments - Quarter 3 Financial Update (2016)
(in thousands of dollars)
The chart below identifies the projects which have received gross budget adjustments, transfers from the capital variance project, budget reductions and transfer to operations during Q3 2016.
Project Description | Total Budget | Capital Adjustments | Adjusted Budget | |||
---|---|---|---|---|---|---|
Gross Budget Adjustment | Transfer From Capital Variance Project |
Budget Reduction | Transfer to Operations | |||
Niagara Regional Police Services Board | ||||||
NRPS - Comms Unit System | $ 205 | $ - | $25 | $ - | $ - | 230 |
Capital Asset Acquisitions | 127 | 35 | - | - | - | 162 |
Public Works - Levy | ||||||
Roads Resurfacing - 2013 PH2 | 2,289 | - | - | (795) | - | 1,494 |
Roads Resurfacing - 2014 PH2 | 2,897 | - | - | (737) | - | 2,160 |
Roads Resurfacing - 2015 | 5,305 | - | - | (800) | - | 4,505 |
Replacement of Burgoyne Bridge * | 93,450 | 70 | - | - | (300) | 93,220 |
Intersection - RR20 Industrial Park/South Grimsby Road 6 | 1,750 | 42 | 710 | - | - | 2,802 |
Roads Rehabilitation - RR 14 RR20/Townline | 6,822 | 58 | - | - | - | 6,880 |
Structural Rehabilitation - 027220 Main Street Bridge | 5,600 | 253 | - | (1,150) | - | 4,703 |
Capacity Improvements - Reconstruct RR 89 Homer/NOTG | 2,720 | 88 | - | - | - | 2,808 |
Intersection - RR18 Ontario St/RR40 South Service Road | 230 | - | 41 | - | - | 271 |
2016 Annual - Illumination Installation | 450 | - | - | - | (150) | 300 |
102-TSR/Valley Way Ph3-NF | 7,998 | 65 | 177 | - | - | 8,240 |
Wastewater | ||||||
Pump Station Improvement Program - Ontario Street | 1,213 | 13 | - | (440) | - | 786 |
Pump Station Improvement Program - Fretz Street | 1,700 | - | 60 | - | - | 1,760 |
Sewer & Forcemain Program - Confederation Park | 2,500 | - | - | (675) | - | 1,825 |
Wastewater Treatment Plant Upgrade - Smithville Lagoon | 100 | - | 120 | - | - | 220 |
Water Works | ||||||
Decommissioning obsolete equipment | 1,113 | - | 75 | - | - | 1,188 |
Water Treatment Plant Upgrade - Grimsby | 353 | - | 40 | - | - | 393 |
Water Treatment Plant Upgrade - Decew Falls - 2010 | 9,000 | - | - | (540) | - | 8,460 |
$ 145,821 | $ 924 | $ 1,248 | $ (5,137) | $ (450) | $ 142,406 |