A detailed analysis of capital sub-projects with budgets remaining greater than $1 million is presented below. There are a total of 171 projects totalling $832.4 million of approved capital budget. Project spending to date on these sub-projects amounts to $449.9 million, representing 54.0 per cent of the approved capital budget on these sub-projects.
Project Description | Total Budget | Transfer From Capital Variance Project | Adjusted Budget | Project-to-date Actuals | Budget Remaining | Forecasted Cashflows | Estimated Year of Completion | |
---|---|---|---|---|---|---|---|---|
2016 | Beyond 2016 | |||||||
Community Services | ||||||||
LTC Home Redevelopment | $ 3,515,000 | $ - | $ 3,515,000 | $ 44,461 | $ 3,470,539 | $ 100,000 | $ 3,370,539 | 2017 |
Northland Pointe Siding Replacement | 4,700,000 | - | 4,700,000 | 2,574,927 | 2,125,073 | 1,000,000 | 700,000 | 2017 |
Total Community Services | 8,215,000 | - | 8,215,000 | 2,619,387 | 5,595,613 | 1,100,000 | 4,070,539 | |
Corporate Services | ||||||||
Asset Replacement - 2016 | 3,168,500 | - | 3,168,500 | 194,214 | 2,974,286 | 2,974,286 | - | 2016 |
Financial Management System | 12,940,000 | - | 12,940,000 | 11,380,649 | 1,559,351 | 559,351 | 1,000,000 | 2017 |
GO Transit & Other Transportation | 10,000,000 | - | 10,000,000 | - | 10,000,000 | 4,000,000 | 6,000,000 | 2018 |
Information Technology Server Building | 3,700,000 | 245,000 | 3,945,000 | 305,567 | 3,639,433 | 1,819,717 | 1,819,716 | 2017 |
Renewable Energy Program | 1,366,000 | - | 1,366,000 | - | 1,366,000 | 465,000 | 50,000 | 2017 |
Total Corporate Services | 31,174,500 | 245,000 | 31,419,500 | 11,880,431 | 19,539,069 | 9,818,354 | 8,869,716 | |
Court Services | ||||||||
Court Facilities Renewal | 26,600,000 | - | 26,600,000 | 1,961,636 | 24,638,364 | 425,000 | 24,245,189 | 2019 |
Total Court Services | 26,600,000 | - | 26,600,000 | 1,961,636 | 24,638,364 | 425,000 | 24,245,189 | |
Niagara Regional Housing | ||||||||
Building Capital - 2014 | 2,098,157 | - | 2,098,157 | 1,948,702 | 149,455 | 48,524 | 100,930 | 2017 |
Building Capital - 2015 | 2,045,279 | - | 2,045,279 | 1,039,950 | 1,005,329 | 691,024 | 314,305 | 2017 |
Building Capital - 2016 | 2,442,568 | - | 2,442,568 | 993,400 | 1,449,168 | 1,610,787 | - | 2016 |
Fitch Street, Welland | 9,982,623 | - | 9,982,623 | 9,318,195 | 664,428 | - | - | 2016 |
New Development | 11,592,000 | - | 11,592,000 | 1,092,229 | 10,499,771 | 950,630 | 11,733,930 | 2018 |
Unit Capital - 2015 | 2,622,000 | - | 2,622,000 | 1,481,103 | 1,140,897 | 219,292 | 921,605 | 2017 |
Unit Capital - 2016 | 2,389,750 | - | 2,389,750 | 154,769 | 2,234,981 | 1,997,545 | 75,000 | 2017 |
Total Niagara Regional Housing | 33,172,377 | - | 33,172,377 | 16,028,348 | 17,144,029 | 5,517,802 | 13,145,770 | |
Niagara Regional Police Services | ||||||||
Communications Unit Back-up | 2,250,000 | - | 2,250,000 | - | 2,250,000 | - | 2,250,000 | 2018 |
Communications Unit Equipment | 4,500,000 | - | 4,500,000 | 2,305,160 | 2,194,840 | 2,194,840 | - | 2016 |
Enterprise Content Management | 2,800,000 | - | 2,800,000 | 2,643,744 | 156,256 | 156,256 | - | 2016 |
IT Continuity Plan | 1,500,000 | - | 1,500,000 | 533,724 | 966,276 | 400,000 | 566,276 | 2017 |
Long-term Accommodations - Headquarters | 83,076,000 | - | 83,076,000 | 63,663,346 | 19,412,654 | 5,018,097 | 14,414,900 | 2017 |
S.P.I.R.I.T. | 8,630,100 | - | 8,630,100 | 8,358,190 | 271,910 | 26,445 | 245,466 | 2017 |
Vehicles - 2012 | 1,620,000 | - | 1,620,000 | 1,618,751 | 1,249 | 1,249 | - | 2016 |
Vehicles - 2013 | 1,300,000 | - | 1,300,000 | 1,220,102 | 79,898 | 79,898 | - | 2016 |
Vehicles - 2014 | 1,423,000 | - | 1,423,000 | 1,422,527 | 473 | 473 | - | 2016 |
Vehicles - 2015 | 1,400,000 | - | 1,400,000 | 1,361,995 | 38,005 | 38,005 | - | 2016 |
Vehicles - 2016 | 1,400,000 | - | 1,400,000 | 261,495 | 1,138,505 | 965,618 | 172,887 | 2017 |
Voice Radio System | 13,000,000 | - | 13,000,000 | 9,634,672 | 3,365,328 | 3,365,328 | - | 2016 |
Total Niagara Regional Police Services | 122,899,100 | - | 122,899,100 | 93,023,707 | 29,875,393 | 12,246,209 | 17,649,529 | |
Public Health | ||||||||
Ambulance & Equipment - 2015 | 1,970,097 | - | 1,970,097 | 1,620,399 | 349,698 | 139,794 | - | 2016 |
Ambulance & Equipment - 2016 | 1,766,008 | - | 1,766,008 | 2,898 | 1,763,110 | 1,473,093 | 160,000 | 2017 |
Emergency Medical Services Facility - Thorold | 2,000,000 | - | 2,000,000 | 1,656,292 | 343,708 | 25,000 | - | 2016 |
Emergency Medical Services Facility - Welland | 1,100,000 | - | 1,100,000 | 8 | 1,099,992 | - | 1,099,992 | 2017 |
EMS Equipment - 2015 | 2,262,440 | - | 2,262,440 | 1,763,029 | 499,411 | 84,000 | - | 2016 |
Facilities - Fort Erie | 286,353 | - | 286,353 | 146,263 | 140,090 | 140,090 | - | 2016 |
Facilities - Niagara Falls | 4,378,647 | - | 4,378,647 | 709,806 | 3,668,841 | 1,668,841 | 2,000,000 | 2017 |
Facilities - Niagara Region | 3,500,000 | - | 3,500,000 | - | 3,500,000 | - | 3,500,000 | 2017 |
Total Public Health | 17,263,545 | - | 17,263,545 | 5,898,695 | 11,364,850 | 3,530,818 | 6,759,992 | |
Public Works - Levy | ||||||||
Inter-municipal Transit - Capital Acquisitions - 2015 | 1,340,000 | - | 1,340,000 | - | 1,340,000 | 1,340,000 | - | 2016 |
Inter-municipal Transit - Capital Acquisitions -2010 | 3,700,000 | - | 3,700,000 | 3,561,546 | 138,454 | 93,790 | - | 2016 |
Vehicles | 3,543,000 | - | 3,543,000 | - | 3,543,000 | 2,873,859 | 610,000 | 2017 |
Annual - Development | 1,000,000 | - | 1,000,000 | - | 1,000,000 | 128,000 | - | 2016 |
Annual - Transportation Master Plans | 1,400,000 | - | 1,400,000 | 547,715 | 852,285 | 200,000 | 652,285 | 2017 |
Capacity Improvements - New Escarpment Crossing | 1,670,000 | 530,000 | 2,200,000 | 682,030 | 1,517,970 | 25,000 | 1,475,000 | 2018 |
Capacity Improvements - Reconstruct Hwy 406 @ Third Interchange | 1,450,000 | - | 1,450,000 | 727,373 | 722,627 | 10,000 | 712,627 | 2017 |
Capacity Improvements - Reconstruct QEW @ Glendale Ave Interchange | 1,000,000 | - | 1,000,000 | 891 | 999,109 | - | 999,109 | 2018 |
Capacity Improvements - Reconstruct RR 49 (McLeod), Montrose to Stanley | 9,875,883 | - | 9,875,883 | 43,651 | 9,832,232 | 800,000 | 9,032,000 | 2017 |
Capacity Improvements - Reconstruct RR 49 Concession 6/Eastwest Line | 1,600,000 | - | 1,600,000 | 233,959 | 1,366,041 | 366,041 | 1,000,000 | 2017 |
Capacity Improvements - Reconstruct RR 57 (Thorold Stone) east of Stanley | 19,047,810 | - | 19,047,810 | 18,311,131 | 736,680 | 736,680 | - | 2016 |
Capacity Improvements - Reconstruct RR 77, Vansickle to First | 10,848,737 | 663,083 | 11,511,820 | 10,532,348 | 979,472 | 479,839 | - | 2016 |
Capacity Improvements - Reconstruct RR 89 Homer/NOTG | 2,720,000 | - | 2,720,000 | 1,147,498 | 1,572,502 | 1,000,000 | 500,000 | 2017 |
Intersection - King at Greenlane and Durham (Roundabout) | 3,038,500 | - | 3,038,500 | 1,517,198 | 1,521,302 | 1,200,000 | 300,000 | 2017 |
Intersection - RR20 Highland/Main | 3,077,837 | 165,404 | 3,243,241 | 3,051,007 | 192,234 | 92,000 | 100,000 | 2017 |
Intersection - RR20 Industrial Park/South Grimsby Road 6 | 1,750,000 | - | 1,750,000 | 302,963 | 1,447,037 | 100,000 | 1,347,037 | 2017 |
Intersection - RR20 Lundys Lane/Garner Road | 1,400,000 | - | 1,400,000 | 1,442,387 | (42,387) | - | - | 2016 |
Intersection - RR46 Geneva/St. Paul | 1,500,000 | - | 1,500,000 | 93,342 | 1,406,658 | 500,000 | 906,658 | 2017 |
Intersection - RR89 Jacobsen/Burleigh | 1,500,000 | - | 1,500,000 | 226,784 | 1,273,216 | 500,000 | 773,000 | 2017 |
Replacement of Burgoyne Bridge | 93,450,000 | - | 93,450,000 | 67,195,674 | 26,254,326 | 20,000,000 | 6,255,021 | 2017 |
Roads Reconstruction - RR20 Station/Rice | 3,793,011 | - | 3,793,011 | 3,421,566 | 371,445 | - | 311,000 | > 2019 |
Roads Reconstruction - RR3 Central/Concession | 2,445,591 | - | 2,445,591 | 2,345,640 | 99,951 | 99,951 | - | 2016 |
Roads Reconstruction - RR38 QEW/Fourth | 3,070,000 | 140,000 | 3,210,000 | 1,337,218 | 1,872,782 | 872,782 | 1,000,000 | 2017 |
Roads Reconstruction - RR50 Thorold/Riverbank | - | 2,400,000 | 2,400,000 | 16,248 | 2,383,752 | 2,000,000 | 383,752 | 2017 |
Roads Rehabilitation - RR 1 Albert/Lakeshore | 1,125,000 | - | 1,125,000 | 145,374 | 979,626 | 400,000 | 579,000 | 2017 |
Roads Rehabilitation - RR 1 Dominion Road, Burleigh/Buffalo | 9,425,000 | 1,700,000 | 11,125,000 | 149,270 | 10,975,730 | 1,000,000 | 9,975,730 | 2018 |
Roads Rehabilitation - RR 14 RR20/Townline | 6,705,434 | 116,566 | 6,822,000 | 6,653,525 | 168,475 | 100,000 | 68,475 | 2017 |
Roads Rehabilitation - RR 18 (Mountain), George to King | 8,245,223 | - | 8,245,223 | 4,715,579 | 3,529,644 | 3,000,000 | 529,644 | 2017 |
Roads Rehabilitation - RR 20 Lookout/Haist | 5,285,000 | - | 5,285,000 | 4,887,737 | 397,263 | 200,000 | 197,263 | 2017 |
Roads Rehabilitation - RR 45 RR4/RR63 | 1,775,000 | - | 1,775,000 | 29,790 | 1,745,210 | 120,000 | 1,621,968 | 2019 |
Roads Rehabilitation - RR 87 Lake/Geneva | 7,420,000 | - | 7,420,000 | 563,767 | 6,856,233 | 3,000,000 | 3,856,233 | 2018 |
Roads Rehabilitation - RR 87 Lakeport/Lake | 5,637,725 | - | 5,637,725 | 5,569,954 | 67,771 | 30,000 | 37,771 | 2017 |
Roads Rehabilitation - RR 87 Third/Henley | 3,469,671 | - | 3,469,671 | 3,195,499 | 274,172 | 174,172 | 100,000 | 2017 |
Roads Rehabilitation - RR 87 Third/Seventh | 1,500,000 | - | 1,500,000 | 240,912 | 1,259,088 | 200,000 | 1,059,088 | 2017 |
Roads Rehabilitation - RR 87 Townline/Four Mile Creek | 1,750,000 | - | 1,750,000 | 335,040 | 1,414,960 | 1,000,000 | 414,960 | 2017 |
Roads Resurfacing - 2013 | 5,718,911 | - | 5,718,911 | 4,188,524 | 1,530,387 | 1,100,000 | 430,387 | 2017 |
Roads Resurfacing - 2014 | 4,850,000 | 2,375,000 | 7,225,000 | 6,122,518 | 1,102,482 | 1,000,000 | 100,000 | 2016 |
Roads Resurfacing - 2015 | 9,446,000 | - | 9,446,000 | 7,627,108 | 1,818,892 | 1,300,000 | 500,000 | 2017 |
Roads Resurfacing - 2016 | 9,000,000 | 800,000 | 9,800,000 | 84,122 | 9,715,878 | 7,700,000 | 2,000,000 | 2017 |
Structural Rehabilitation - 027220 Main Street Bridge | 5,600,000 | - | 5,600,000 | 4,345,924 | 1,254,076 | 200,000 | 100,000 | 2017 |
Structural Rehabilitation - 069205 Reece | 6,032,500 | - | 6,032,500 | 517,434 | 5,515,066 | 200,000 | 5,315,066 | 2018 |
Structural Rehabilitation - 124205 (Central Ave) over Candian National Railroad | 13,655,867 | 3,058,413 | 16,714,280 | 9,727,801 | 6,986,480 | 6,500,000 | 486,480 | 2017 |
Structural Rehabilitation - Ontario Power Generation Bridges over Gibson Lake | 11,600,000 | - | 11,600,000 | 7,061,273 | 4,538,727 | 4,000,000 | 538,727 | 2017 |
Structural Rehabilitation - RR14 Warner | 5,090,000 | - | 5,090,000 | 1,241,359 | 3,848,641 | 500,000 | 3,347,831 | 2017 |
Total Public Works - Levy | 297,551,700 | 11,948,466 | 309,500,166 | 184,140,678 | 125,359,488 | 65,142,113 | 57,616,112 | |
Waste Management | ||||||||
Bridge St - Public Drop Off Depot Improvement | 1,145,000 | - | 1,145,000 | - | 1,145,000 | - | 1,145,000 | 2019 |
Humberstone - Environmental Assessment | 1,000,000 | - | 1,000,000 | 934,775 | 65,225 | 30,000 | - | 2016 |
Humberstone - Landfill Gas Collection | 5,590,000 | 360,000 | 5,950,000 | 3,507,131 | 2,442,869 | - | 2,100,000 | 2018 |
Recycling Centre - Facility Improvements | 1,600,000 | - | 1,600,000 | 888,652 | 711,348 | 140,000 | 350,000 | 2017 |
Recycling Centre - Facility Improvements Groundwater | 1,123,259 | - | 1,123,259 | 933,407 | 189,852 | 50,000 | - | 2016 |
Recycling Centre - Facility Improvements Optical Sorter | 2,222,600 | 495,000 | 2,717,600 | 2,297,714 | 419,886 | - | - | 2017 |
Total Waste Management | 12,680,859 | 855,000 | 13,535,859 | 8,561,679 | 4,974,180 | 220,000 | 3,595,000 | |
Wastewater | ||||||||
Centralized Maintenance Facility Improvements | 1,000,000 | - | 1,000,000 | - | 1,000,000 | - | 1,000,000 | 2018 |
Combined Sewer Overflow (CSO) - Grimsby | 1,725,000 | - | 1,725,000 | 221,707 | 1,503,293 | - | 1,500,000 | 2018 |
Combined Sewer Overflow (CSO) - OAW Separation | 1,350,000 | - | 1,350,000 | 644,703 | 705,297 | 425,000 | - | 2016 |
Combined Sewer Overflow (CSO) - Tank Construction - Chippawa | 9,510,854 | - | 9,510,854 | 9,004,440 | 506,414 | 506,414 | - | 2016 |
Forcemain Replacement - Stevensville | 1,675,000 | - | 1,675,000 | 696,632 | 978,369 | 894,619 | 83,750 | 2017 |
Miscellaneous Program - Biogas Utilization | 1,080,000 | - | 1,080,000 | - | 1,080,000 | - | 1,080,000 | 2018 |
Miscellaneous Program - Garner Road | 2,200,000 | - | 2,200,000 | 29,404 | 2,170,596 | 100,000 | 2,070,596 | 2017 |
Pump Station Capacity Expansion Program - Odour Control - Smithville | 1,500,000 | - | 1,500,000 | 46,609 | 1,453,391 | 50,000 | 1,403,391 | 2017 |
Pump Station Improvement Program - Carleton Street | 2,000,000 | - | 2,000,000 | 84,113 | 1,915,887 | 515,887 | 1,400,000 | 2018 |
Pump Station Improvement Program - Clarke Street | 1,900,000 | - | 1,900,000 | 1,198,570 | 701,430 | 701,430 | - | 2016 |
Pump Station Improvement Program - Design | 2,750,000 | - | 2,750,000 | 1,628,256 | 1,121,744 | 121,744 | 1,000,000 | 2017 |
Pump Station Improvement Program - Fretz Street | 1,700,000 | - | 1,700,000 | 1,456,241 | 243,759 | 243,759 | - | 2016 |
Pump Station Improvement Program - Jordan Valley | 1,609,702 | - | 1,609,702 | 1,486,438 | 123,264 | 95,000 | 10,000 | 2017 |
Pump Station Improvement Program - NOTL, Garrison Rd, William St | 3,667,453 | - | 3,667,453 | 3,130,127 | 537,326 | 537,326 | - | 2016 |
Pump Station Improvement Program - Old Orchard | 1,700,000 | - | 1,700,000 | 138,208 | 1,561,792 | 13,062 | 1,548,730 | 2017 |
Pump Station Improvement Program - Ontario Street | 5,856,027 | - | 5,856,027 | 4,816,284 | 1,039,744 | 582,226 | - | 2016 |
Pump Station Improvement Program - South Side High Lift | 5,900,000 | 750,689 | 6,650,689 | 1,782,379 | 4,868,310 | 3,250,000 | 1,618,310 | 2018 |
Pump Station Improvement Program - Victoria Avenue | 3,600,000 | - | 3,600,000 | 3,190,384 | 409,616 | 31,000 | - | 2016 |
Pump Station Improvement Program - Wellandvale | 2,123,553 | - | 2,123,553 | 988,942 | 1,134,611 | 100,000 | 1,034,611 | 2018 |
Pump Station Improvement Program - Woodsview | 2,420,000 | - | 2,420,000 | 251,455 | 2,168,545 | 26,967 | 2,141,578 | 2018 |
Sewer & Forcemain Program - Confederation Park | 2,500,000 | - | 2,500,000 | 1,597,574 | 902,426 | 850,000 | 52,426 | 2017 |
Sewer & Forcemain Program - Park Road | 13,940,000 | - | 13,940,000 | 11,334,611 | 2,605,389 | 1,000,000 | - | 2016 |
Sewer & Forcemain Program - Stamford Centre | 2,250,000 | - | 2,250,000 | 26,183 | 2,223,817 | 2,223,817 | - | 2016 |
Sewer & Forcemain Program - Victoria Ave | 4,400,000 | - | 4,400,000 | 11,055 | 4,388,945 | 4,300,000 | 88,945 | 2017 |
Sewer Relining Program | 1,426,678 | - | 1,426,678 | 1,301,027 | 125,651 | 125,651 | - | 2016 |
Wastewater Treatment Plant - Capacity Expansion - Niagara-on-the-Lake | 47,031,800 | - | 47,031,800 | 36,080,772 | 10,951,028 | 4,442,276 | 3,867,136 | 2018 |
Wastewater Treatment Plant Digester/Sludge Management | 1,000,000 | - | 1,000,000 | 879,991 | 120,009 | 120,000 | - | 2016 |
Wastewater Treatment Plant Bar Screen Program - Port Weller | 2,725,000 | 190,000 | 2,915,000 | 2,421,774 | 493,226 | 270,000 | 150,000 | 2017 |
Wastewater Treatment Plant Upgrade - Garner Road | 2,200,000 | - | 2,200,000 | 11,422 | 2,188,578 | 150,000 | 2,038,578 | 2017 |
Wastewater Treatment Plant Upgrade - Niagara Falls | 2,100,000 | - | 2,100,000 | 1,913 | 2,098,087 | 115,000 | 1,980,000 | 2018 |
Wastewater Treatment Plant Upgrade - Port Weller | 9,900,000 | - | 9,900,000 | 143,373 | 9,756,627 | 450,000 | 9,306,627 | 2019 |
Wastewater Treatment Plant Upgrade - Welland | 20,500,000 | - | 20,500,000 | 2,525,620 | 17,974,380 | 3,000,000 | 14,974,380 | 2018 |
Wastewater Treatment Plant Upgrade Program - Fine Bubble Aeration - Port Dalhousie | 1,500,000 | - | 1,500,000 | 3,479 | 1,496,521 | 210,000 | 1,286,521 | 2019 |
Wastewater Treatment Plant Upgrade Program - Laneway Upgrades - Port Dalhousie | 2,000,000 | - | 2,000,000 | 204,901 | 1,795,099 | 1,650,000 | 145,099 | 2017 |
Total Wastewater | 168,741,069 | 940,689 | 169,681,758 | 87,338,590 | 82,343,168 | 27,101,179 | 49,780,677 | |
Water Works | ||||||||
Centralized Maintenance Facility Improvements | 1,000,000 | - | 1,000,000 | - | 1,000,000 | - | 1,000,000 | 2018 |
Decommissioning obsolete equipment | 1,000,000 | 112,877 | 1,112,877 | 557,678 | 555,199 | 555,199 | - | 2016 |
Electrical & mechanical upgrades | 1,200,000 | - | 1,200,000 | 1,174,016 | 25,984 | - | - | 2016 |
Elevated Tank repair & painting | 1,900,000 | - | 1,900,000 | 17,378 | 1,882,622 | 500,000 | 1,382,622 | 2018 |
Miscellaneous Program - Reservoir - Stevensville | 1,260,000 | - | 1,260,000 | 102,693 | 1,157,307 | - | - | 2017 |
Miscellaneous Program - System Storage - Grimsby | 1,339,174 | - | 1,339,174 | 307,880 | 1,031,294 | 260,000 | 771,294 | 2018 |
Miscellaneous Program - System Storage - Port Colborne | 11,372,906 | 677,094 | 12,050,000 | 2,610,312 | 9,439,688 | 5,700,000 | 1,396,782 | 2018 |
Valve & valve chamber replacement - 2011 | 1,099,447 | - | 1,099,447 | 577,618 | 521,828 | 396,828 | 125,000 | 2017 |
Valve & valve chamber replacement - 2013 | 2,900,000 | - | 2,900,000 | 131,611 | 2,768,389 | 687,950 | 2,080,439 | 2017 |
Water Treatment Plant Upgrade - Decew Falls - 2010 | 9,000,000 | - | 9,000,000 | 8,368,790 | 631,210 | 50,000 | - | 2016 |
Water Treatment Plant Upgrade - Decew Falls - 2016 | 1,250,000 | - | 1,250,000 | 1,218 | 1,248,782 | 50,000 | 1,198,782 | 2019 |
Water Treatment Plant Upgrade - Niagara Falls - 2013 | 5,250,000 | - | 5,250,000 | 1,763,846 | 3,486,154 | 3,486,154 | - | 2016 |
Water Treatment Plant Upgrade - Niagara Falls - 2015 | 2,000,000 | - | 2,000,000 | 5,971 | 1,994,029 | 200,000 | 1,794,029 | 2017 |
Water Treatment Plant Upgrade - Port Colborne | 6,600,000 | - | 6,600,000 | 361,627 | 6,238,373 | 1,000,000 | 5,238,373 | 2019 |
Water Treatment Plant Upgrade - Rosehill | 11,900,000 | - | 11,900,000 | 498,517 | 11,401,483 | 1,500,000 | 9,901,483 | 2019 |
Water Treatment Plant Upgrade - Welland | 26,605,903 | - | 26,605,903 | 21,688,740 | 4,917,163 | 3,586,868 | 1,330,295 | 2017 |
Watermain Program - Fort Erie, Dominion Road | 4,275,000 | 3,200,000 | 7,475,000 | 1,329 | 7,473,671 | 8 | 7,275,000 | 2018 |
Watermain Program - Welland East and West | 6,200,000 | - | 6,200,000 | 230,043 | 5,969,957 | 3,500,000 | 2,469,957 | 2017 |
Total Water Works | 96,152,429 | 3,989,971 | 100,142,400 | 38,399,267 | 61,743,133 | 21,473,007 | 35,964,056 | |
Total Projects with remaining budgets greater than $1 million | $814,450,578 | $ 17,979,126 | $832,429,704 | $449,852,419 | $382,577,286 | $146,574,482 | $221,696,580 |