Infrastructure Planning and Development Fees
Niagara Region's Infrastructure Planning and Development application fees cover the cost of Regional review of planning applications. Final fees depend on the complete application submission date to the cities / towns and the type and nature of the development.
2026 Review fees
- Pre-consultation review: $620
Engineering
The following fees are consistent with the work included in the 2024 Memorandum of Understanding for the Engineering Function and Review in Niagara.
-
Infrastructure
Description Fee Major Engineering Infrastructure Review
Applications that need a Regional response if the property is on a Regional road, if there are Regional infrastructure / facilities nearby or if the application has a Regional interest. This fee applies to site plans, clearance of conditions for subdivisions and condominiums.$1,365 Minor Engineering Infrastructure Review
Applications needing waste collection reviews, no change to entrances or Regional infrastructure nearby. This fee applies to site plans, consents and minor variances.$590 Engineering Infrastructure Review
This fee applies to subdivisions, condominiums, zoning by-law amendments and Official Plan amendments$780 Functional Servicing Review - Engineering Infrastructure Review $1,365 Functional Servicing Reviews for Secondary Plan / Block Plan and Expansion Areas or applications that need Infrastructure Improvement with Agreement for Development $5,200 Legal Agreement Fee $1,350 Engineering Reviews for Applications that need Regional Infrastructure Improvement $5,050 -
Private services
Description Fee Hydrogeology Review $1,365 Private Sewage System Review for Planning Applications $545 -
Traffic
Description Fee Traffic Review for Secondary Plans / Block Plans $5,200 Traffic Study Review - Minor (entrance / safety / sight lines) $480 Traffic Study Review (Traffic Impact Assessment) $1,400 -
Water and wastewater
Description Fee Water and Wastewater Modelling Design Review Greater of $550, plus disbursements and application of hourly rates applicable to the review of the application Water Service Connection to Regional Infrastructure $1,285 Sanitary and Storm Sewer Lateral Connection to Regional Infrastructure $1,285 Stormwater Management Review for land less than two hectares $725 Stormwater Management Review for land greater than five hectares $2,185 Stormwater Management Review for land less than five hectares $1,365
Environmental, urban design and planning
Fees are subject to planning service agreements with participating area municipalities.
-
Environmental
Description Fee Major Environmental Impact Study Review (two or more features) $3,060 Minor Environmental Impact Study Review (one feature) $1,530 Major Environmental Impact Study Review (two or more features) - No approved terms of reference $4,126 Minor Environmental Impact Study Review (one feature) - No approved Terms of Reference $2,402 Environmental Impact Study Terms of Reference Review $566 Environmental Impact Study Draft Review $566 Environmental Impact Study Addendum Review fee Half of the applicable Environmental Impact Study Review fee Review of Restoration Plan $775 Review of Tree Preservation Plan $403 Review of Monitoring Plan $995 -
Urban design
Description Fee Major Urban Design $1,000 Minor Urban Design $300 -
Local official plan amendments
Description Fee Major Official Plan Amendment Review (three or more types of Provincial / Regional policy reviews) $4,871 Minor Official Plan Amendment Review $2,499 Minor Technical Review $800 -
Subdivisions, vacant land or common element condominiums
Description Fee Draft Plan Review (based on the entire area of the Subdivision or Condominium) $1,826, plus $806 per hectare Revision to submission by applicant before Draft Plan Approval $1,964 Modification of Draft Plan Approval $1,964 Extension of Draft Plan Approval for plans granted approval in or after 2006 $1,423 Clearance of Draft Plan Conditions per phase $1,964 Minor Technical Review $800 Complex File Review $10,500 -
Standard condominiums
Description Fee Draft Plan of Standard Condominium Review $1,811 Revisions to submission by applicant before approval $1,270 Modification of Standard Draft Plan of Condominium Approval $1,270 Extension of Standard Draft Plan of Condominium Approval $908 Clearance of Conditions for Standard Plan of Condominium $1,632 Minor Technical Review $800 -
Zoning by-law amendments
Description Fee Zoning By-law Amendment Review $1,515 Major Revision to Submission by applicant before approval $1,097 Removal of Holding (H) Symbol $913 Minor Technical Review $800 -
Consents
Description Fee Consent Review in Urban Areas $520 Consent Review in Rural / Outside Urban Areas $852 Active consent files formerly under the authority of Niagara Region are subject to a final certification review fee at the request of the local municipality.
-
Site Plans
Description Fee Major Site Plans and Site Plan Amendment Review $1,372 Revision to Submission by applicant (before approval) $796 Clearance of Site Plan Conditions $1,015 Minor Technical Review $800 -
Minor variances
Description Fee Minor Variance Review, excluding Septic and Engineering Infrastructure Review $490 -
Niagara Escarpment Commission development permit applications
Description Fee Development Permit Review $923 Minor Development Permit Review (no Provincial or Regional concerns identified, such as sheds, garages, pools, etc.) $490 -
Environmental site assessments (Brownfield sites)
Description Fee Request to use non-potable water site conditions standard $410 Request to use non-potable water site conditions standard - update letter $150 -
Hydrogeology Review
Description Fee Hydrogeology Review $1,365
More information
- All development applications are circulated to Niagara Region for review, except where the Region has determined through pre-consultation that the development proposal is exempt from further circulation and review in accordance with the Memorandum of Understanding - Engineering Function and Review and Planning Service Agreements
- All development review / processing fees must be received by Public Works before the Region's submission of comment / recommendations and / or planning advice to the local municipality
- Niagara Region's review / processing fees are not refundable if an application is refused or only partially approved by the approval authority
- Niagara Region's review / processing fees may be returned if the applicant voluntarily withdraws the application before staff start the review process
- In addition to development review fees, Niagara Region may require the applicant to cover the cost of peer review for specific technical studies as applicable
- All development applications initiated by a local municipality are exempt from Niagara Region's development review fees
- Wainfleet, Welland and West Lincoln do their own private sewage system review and, therefore, the Regional private septic system review fee is not applicable